The motorway works further along are to do with the Woodside viaducts, the Sighthill Bridge hasn't had much impact.

(From what I remember there were a couple of overnight closures to demolish the original bridge, and wheel the new one into place)

Woodside is quite a job - equivalent to what was done on the Kingston Bridge in the late 90's. They're jacking up the bridge deck on temporary supports, then renewing some components underneath, all whilst keeping traffic running. There's some impressive looking engineering going on.
Reddit Linkhttps://www.reddit.com/r/glasgow/comments/11yfvt0/new_bridge_to_sighthill_is_open/jd865dw/